127EAW26R0001 - Brush Creek Work Center Construction
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service is soliciting proposals for the Brush Creek Work Center Construction (Solicitation 127EAW26R0001) in Berry Creek, CA. This project involves decommissioning existing facilities and constructing a new work center, including utility infrastructure. The estimated magnitude of the construction is more than $10,000,000. This is a Total Small Business Set-Aside.
Scope of Work
The project requires the contractor to provide all labor, tools, materials, and equipment for the demolition of specified existing Plumas National Forest facilities and the construction of a complete new work center. Key construction items include:
- Engine Garage, Barracks, Warehouse, Storage Container, Seeding Cooler & Canopy, Hazmat Storage, Pump House, and Trash Enclosure construction.
- Installation of site utilities (water, sewer, electrical) and landscaping.
- Five optional construction items are also included, confirmed as "adds." Work must adhere strictly to specifications, drawings, and industry standards, including specific requirements for a Fire Plan, Spill Plan, Equipment Cleaning, and compliance with State law during fire season. Ground-disturbing activities are permitted year-round.
Contract Details
- Contract Type: Firm-Fixed-Price
- Period of Performance: 650 calendar days after Notice to Proceed.
- Set-Aside: Total Small Business Set-Aside (FAR 19.5).
- Eligibility: Offerors must possess a California General Contractors License Type B or equivalent from another state.
- Place of Performance: 12815 Oro Quincy Highway, Berry Creek, CA 95916.
Submission & Evaluation
Proposals must be submitted via email to Gregory.Cunningham@usda.gov. Required submission components include:
- Completed SF1442.
- Price Proposal (using the latest Schedule of Items, REVISION 002).
- Project Schedule of Values.
- Technical Proposal.
- Bid Guarantee (20% of bid price or $1,000,000, whichever is less). Proposals will be evaluated based on Past Performance (recency extended to 5 years), Work Plan/Technical Approach, Key Personnel, Performance Schedule, and Price. Award will be made to the responsible offeror whose proposal is determined to be best-valued. Page limitations apply for Factor 2 (10 pages) and Factor 4 (3 pages).
Key Dates & Amendments
- Proposal Due Date: April 2, 2026, at 1:00 PM Pacific Time.
- Site Visit: A site visit was held on February 25, 2026, but attendance was not mandatory.
- RFI Log: The latest RFI Log (dated 3.27.2026) provides crucial clarifications and amendments, including the provision of environmental reports (Asbestos/Lead Paint, Geotechnical).
Important Notes
Liquidated damages for delay are $1,137.77 per calendar day. Prevailing wages, as per the Davis-Bacon Act (General Decision Number CA20260007), apply. Contractors are responsible for site security.