ATLANTIC UNDERSEA TEST AND EVALUATION CENTER (AUTEC) WATER TANKS REPLACEMENT, ALANTIC UNDERSEA TEST AND EVALUATION CENTER (AUTEC), ANDROS ISLAND, BAHAMAS

SOL #: N6945026R0006Solicitation

Overview

Buyer

Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM SOUTHEAST
NAS JACKSONVILLE, FL, 32212-0030, United States

Place of Performance

Place of performance not available

NAICS

Water and Sewer Line and Related Structures Construction (237110)

PSC

Repair Or Alteration Of Water Supply Facilities (Z2NE)

Set Aside

No set aside specified

Timeline

1
Posted
Feb 9, 2026
2
Last Updated
Mar 26, 2026
3
Submission Deadline
Apr 1, 2026, 6:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Navy, NAVFACSYSCOM SOUTHEAST, is soliciting proposals for a Design-Bid-Build (DBB), Firm-Fixed-Price (FFP) construction contract to replace a portion of the potable and fire supply water system at the Atlantic Undersea Test and Evaluation Center (AUTEC) on Andros Island, Bahamas. This project aims to restore the system to its original design intent while updating it for current use. Proposals are due April 1, 2026, at 2:00 PM ET.

Scope of Work

This project involves the replacement of critical water infrastructure. Key components include:

  • Demolition of two existing finished water holding/contact tanks that have reached the end of their useful life, along with abandoned piping.
  • Construction of two new finished water holding/contact tanks, each with a 500,000-gallon capacity.
  • Construction of one new elevated storage tank with a 150,000-gallon capacity.
  • Installation of new interconnecting potable water distribution piping (C900 PVC, 8" diameter or greater). The project requires adherence to specific inspection and quality assurance requirements, including the need for a Special Inspector of Record (SIOR) for Lateral Force Resisting Systems.

Contract Details

  • Contract Type: Design-Bid-Build (DBB), Firm-Fixed-Price (FFP)
  • Period of Performance: 365 calendar days from the date of award.
  • Project Magnitude: Estimated between $10,000,000 and $25,000,000.
  • NAICS Code: 237110 (Water and Sewer Line and Related Structures Construction) with a size standard of $45,000,000.
  • Set-Aside: This procurement is solicited on an unrestricted basis, inviting full and open competition.
  • DPAS Priority Rating: DO-C2.

Submission & Evaluation

Proposals must be submitted via the Procurement Integrated Enterprise Environment (PIEE) portal. The award will be based on a best value determination, considering price and the following non-price factors:

  • Factor 1: Experience (Construction Experience)
  • Factor 2: Past Performance
  • Factor 3: Safety
  • Factor 4: Technical Approach Non-price factors (Experience, Safety, Technical Approach) are of equal importance and combined are equal in importance to Past Performance. The combined non-price factors are approximately equal to price. Offerors must acknowledge Amendment 0001 (updating ProjNet key) and Amendment 0002 (extending due date) in writing with their proposal. Pre-Proposal Inquiries (PPIs) are due ten (10) calendar days prior to the closing date, submitted via ProjNet using the key M9RSTR-XN5SJ3.

Key Attachments & Requirements

Bidders must complete and submit several forms, including:

  • Attachment A: Construction Experience Project Data Sheet.
  • Attachment B: NAVFAC/USACE Past Performance Questionnaire (PPQ-0).
  • Attachment C: Safety Data Sheet, requiring five years of DART/TCR rates and a safety narrative.
  • Drawings: A conformed set of architectural and engineering plans (10.14.25 Set_AUTEC WTP_SubmittalsConform.pdf) is provided to detail the scope.
  • Travel: Attachment F outlines procedures for personnel visiting AUTEC/Andros. Offerors must be registered in SAM, and Performance and Payment Bonds are required.

Contact Information

People

Points of Contact

Delcheia TurnerPRIMARY
Sheila BorgesSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 5
Solicitation
Posted: Mar 26, 2026
View
Version 4Viewing
Solicitation
Posted: Mar 23, 2026
Version 3
Solicitation
Posted: Mar 12, 2026
View
Version 2
Solicitation
Posted: Feb 24, 2026
View
Version 1
Pre-Solicitation
Posted: Feb 9, 2026
View