Banana River, Maintenance Dredging, Brevard County, Florida
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The U.S. Army Corps of Engineers, Jacksonville District, is conducting market research through a Sources Sought notice for Maintenance Dredging in the Banana River, Canaveral Barge Canal, and Kars Park Channel in Brevard County, Florida. This opportunity is restricted to specific contractors holding a contract under Solicitation Number W912EP25R0010 South Atlantic Division Regional Small Business Multiple Award Task Order Contract for Maintenance Dredging. Responses are due by May 28, 2026, at 3:00 PM EST.
Scope of Work
The project involves maintenance dredging at identified areas within the Banana River, Canaveral Barge Canal, and Kars Park Channel. Dredged material will be disposed of in DMMA-2B and DMMA-4. Additional work includes environmental and water quality monitoring. The project is structured with a base bid and three options.
Contract & Timeline
- Type: Sources Sought (Market Research)
- Set-Aside: Total Small Business (FAR 19.5), restricted to specific MATOC holders
- NAICS: 237990 (Dredging and Surface Cleanup Activities) with a $37 Million size standard
- Target Price Range: $10,000,000.00 - $25,000,000.00
- Estimated Period of Performance: 230 calendar days after Notice to Proceed (NTP), including 60 days to commence work.
- Base Bid: 145 calendar days (inclusive of 60 days for mobilization/demobilization)
- Option A: 45 calendar days
- Option B: 20 calendar days
- Option C: 20 calendar days
- RFP Release (Anticipated): On or about July 21, 2026
- Proposals Due (Anticipated): On or about August 20, 2026
- Response Due for Sources Sought: May 28, 2026, 3:00 PM EST
- Published: April 29, 2026
Evaluation
Award of the eventual task order will be made on the basis of Lowest Price Technically Acceptable (LPTA), as stated for the forthcoming Request for Proposal (RFP).
Additional Notes
This is for market research only; no contract will be awarded from this Sources Sought. No reimbursement will be made for response costs. Firms should only respond if they intend to submit a proposal for the future RFP. Responses should be sent directly to Guesley Leger (Guesley.Leger@usace.army.mil) and Ruth Rodriguez (ruth.c.rodriguez@usace.army.mil).