FXI and ISR Mirror Bender Upgrade Package

SOL #: 475273Pre-Solicitation

Overview

Buyer

Energy
Energy, Department Of
BROOKHAVEN NATL LAB -DOE CONTRACTOR
Upton, NY, 11973, United States

Place of Performance

Upton, NY

NAICS

Other Measuring and Controlling Device Manufacturing (334519)

PSC

Optical Instruments, Test Equipment, Components And Accessories (6650)

Set Aside

No set aside specified

Timeline

1
Posted
Jun 3, 2026
2
Response Deadline
Jun 18, 2026, 12:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Energy (DOE), through Brookhaven National Laboratory (BNL), has issued a Presolicitation Notice for the FXI and ISR Mirror Bender Upgrade Package. This opportunity seeks a contractor to design, engineer, manufacture, assemble, test, deliver, install, and test upgraded mirror bender systems for the FXI and ISR Beamlines at the National Synchrotron Light Source II (NSLS-II). This requirement is for full and open competition. The solicitation (Number 475273) is anticipated by the end of June 2026, with an award expected around July 2026.

Scope of Work

The contractor will be responsible for providing new stepper-motor controlled mirror bender systems to replace existing piezo-based units. This includes:

  • FXI Beamline: One (1) Collimating Mirror (CM) Bender System and one (1) Toroidal Mirror (TM) Bender System.
  • ISR Beamline: One (1) Horizontal Focusing Mirror (HFM) Bender and one (1) Vertical Focusing Mirror (VFM) Bender, including in-vacuum, double piping, and metal cooling lines.
  • Provision of cables suitable for ultra-high-vacuum and high X-ray radiation environments. The scope specifically excludes mirror substrates, mirror tanks, and standard NSLS-II motion controllers. Design, manufacturing, and initial testing will occur at the contractor's facility, with final installation and testing at BNL in Upton, NY.

Performance Requirements

All equipment must comply with U.S. standards, NFPA70, and be certified by a Nationally Recognized Testing Laboratory (NRTL). Process piping must adhere to ASME B31.3 or equivalent, and vacuum components must meet BSA document LT-ENG-RSI-SR-VA-002 and be UHV-conditioned. Specific performance requirements for mirror temperature, vibrational stability, bend radius range, actuator resolution, and repeatability are detailed. A two (2) year warranty against failure and defects is required.

Contract & Timeline

  • Opportunity Type: Presolicitation (Solicitation Number 475273)
  • Anticipated Contract Type: Firm Fixed Price
  • Set-Aside: Full and Open Competition
  • NAICS: 334519 (Optical Instrument and Lens Manufacturing, Size Standard: 600 employees)
  • PSC: 6650 (Optical Instruments, Test Equipment, Components And Accessories)
  • Solicitation Release: Anticipated by end of June 2026
  • Anticipated Award: Around July 2026
  • Site Acceptance: Approximately 38 weeks (9 months) after contract award.

Milestones & Deliverables

  • Final Design Review (FDR) report: 8 weeks after contract award.
  • Equipment delivery: 32 weeks after contract award.
  • Installation and testing: 38 weeks after contract award.
  • End item documentation package: To be provided with equipment delivery.

Additional Notes

Interested parties must be registered in the System for Award Management (SAM) under NAICS 334519 prior to submitting quotes for the future solicitation. This notice is for planning purposes only and does not constitute a solicitation. Contact Marie J. Williams at mwilliams3@BNL.GOV for inquiries.

People

Points of Contact

Marie J. WilliamsPRIMARY

Files

Files

Download
Download

Versions

Version 1Viewing
Pre-Solicitation
Posted: Jun 3, 2026
FXI and ISR Mirror Bender Upgrade Package | GovScope