Gulf Intracoastal Waterway, Texas Matagorda to Corpus Christi Bay with Goose Island BUS Placement Pipeline Dredging

SOL #: W912HY26BA023Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W076 ENDIST GALVESTON
GALVESTON, TX, 77550-1229, United States

Place of Performance

Corpus Christi, TX

NAICS

Other Heavy and Civil Engineering Construction (237990)

PSC

Maintenance Of Dredging Facilities (Z1KF)

Set Aside

No set aside specified

Timeline

1
Posted
Mar 10, 2026
2
Last Updated
May 6, 2026
3
Submission Deadline
May 27, 2026, 3:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers (USACE), Galveston District, has issued a pre-solicitation notice for a Firm-Fixed Price contract for maintenance pipeline dredging of the Gulf Intracoastal Waterway (GIWW) in Texas, specifically from Matagorda to Corpus Christi Bay. This is an unrestricted, full, and open competition opportunity, with an estimated magnitude between $5,000,000.00 and $10,000,000.00. The solicitation is anticipated in April 2026, with responses due on or about May 27, 2026.

Scope of Work

The project involves pipeline dredging in Calhoun and Aransas counties, Texas. Key requirements include a production rate of 10,000 Cubic Yards (CY) per day. Dredged material will be placed in semi-confined, open water, and beneficial use sites. The estimated completion time is 91 calendar days, with potential for an additional 96 calendar days through three options. Liquidated damages will apply for delays.

Contract Details

  • Contract Type: Firm-Fixed Price
  • Estimated Magnitude: Between $5,000,000.00 and $10,000,000.00
  • NAICS Code: 237990 (Dredging)
  • Small Business Size Standard: $45,000,000.00
  • Bonds: Performance and Payment Bonds required within 5 calendar days after award.
  • Start Work: Contractor must begin work within 10 calendar days after acknowledgement of the Notice to Proceed.

Submission & Evaluation

  • Solicitation Release: On or about April 2026.
  • Response Date: On or about May 27, 2026.
  • Submission Method: Bids must be submitted via the Procurement Integrated Enterprise Environment (PIEE) Solicitation Module.
  • Pre-Award Documents: Must be furnished within 2 working days after Bid Opening.
  • Recommendation: Offers should be submitted at least 2 hours prior to the response time to allow for electronic transmission.

Eligibility / Set-Aside

  • Competition Type: Unrestricted, full, and open competition.
  • Registration: Offerors must be registered with the System for Award Management (SAM).

Notes

Plans and specifications will not be available in paper format; they must be downloaded from the PIEE suite. Offerors are responsible for monitoring the PIEE Solicitation Module daily for updates. A notarized letter appointing the Authorized Entity Administrator is required for SAM registration activation.

People

Points of Contact

Files

Files

View
View
View
View
Download

Versions

Version 3Viewing
Solicitation
Posted: May 6, 2026
Version 2
Solicitation
Posted: Apr 22, 2026
View
Version 1
Pre-Solicitation
Posted: Mar 10, 2026
View
Gulf Intracoastal Waterway, Texas Matagorda to Corpus Christi Bay with Goose Island BUS Placement Pipeline Dredging | GovScope