Hydraulic Turbine Runner for Units A2 and N7 for H

SOL #: 140R3026R0016Solicitation

Overview

Buyer

Interior
Bureau Of Reclamation
LOWER COLORADO REGIONAL OFFICE
BOULDER CITY, NV, 89005, United States

Place of Performance

Place of performance not available

NAICS

Turbine and Turbine Generator Set Units Manufacturing (333611)

PSC

Generators And Generator Sets, Electrical (6115)

Set Aside

No set aside specified

Timeline

1
Posted
Jun 10, 2026
2
Submission Deadline
Aug 11, 2026, 12:00 AM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Interior, Bureau of Reclamation, is soliciting for the manufacturing and delivery of two 196,000 HP hydraulic turbine runners for Units A2 and N7 at Hoover Dam. This is an Unrestricted – Sole Source procurement, justified by critical operational needs due to historically low water levels in Lake Mead. The contract is anticipated to be a Firm-Fixed-Price award to Andritz Hydro.

Scope of Work

The requirement includes the manufacturing and delivery of two stainless-steel wide-head range turbine runners (one counterclockwise for Unit A2, one clockwise for Unit N7), along with associated runner cones, coupling bolts, and a roughening air system. The scope also covers the supply and in-place machining of four stationary seal rings, and the provision of a contractor engineer to witness performance testing. The new runners must be hydraulically and dimensionally identical to existing Wide-Head designs.

Contract Details & Timeline

  • Contract Type: Firm-Fixed-Price, Sole Source
  • Set-Aside: Unrestricted – Sole Source (to Andritz Hydro)
  • Period of Performance: 730 calendar days (approximately 2 years) after notice to proceed, anticipated from December 15, 2026, to December 14, 2028. Manufacturing and installation is estimated to take at least 18 months.
  • Mandatory Requirements: Performance and Payment Bonds (SF 25/25A), a Subcontracting Plan (FAR 52.219-9), and a Release of Claims form (DI-137) prior to final payment.
  • Key Dates:
    • Written Questions Due: June 26, 2026 (email virginia_toledo@ios.doi.gov)
    • Proposal Submission Deadline: August 10, 2026, 1700 local time

Evaluation

Evaluation will focus on Total Evaluated Price, Price Reasonableness, and Unbalanced Pricing for the sole source offer. The Contracting Officer will conduct price analysis, cost analysis, and consider commercial factors, including current steel market conditions and specialized machining trends.

Special Requirements

Contractors must comply with specified material standards (ASTM, SAE, ANSI), extensive submittal requirements (RSNs), non-destructive testing (NDT), and welding standards (AWS D1.1/D1.6, ASME BPVC Section IX). A 3-year warranty is required. On-site work at Hoover Dam necessitates security clearances (PIV cards) and adherence to safety standards (OSHA, RSHS, HECP). The prevailing wage rates outlined in Wage Determination NV20260024 for Clark County, Nevada, must be factored into cost proposals. Mobilization and preparatory work payment is addressed, not to exceed 5% of the total proposed price.

People

Points of Contact

Gallardo, LuisPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 1Viewing
Solicitation
Posted: Jun 10, 2026
Hydraulic Turbine Runner for Units A2 and N7 for H | GovScope