MOF Williams River at Tea Creek Bridge Replacement
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service is soliciting bids for the MOF Williams River at Tea Creek Bridge Replacement project in the Monongahela National Forest, Pocahontas County, West Virginia. This Total Small Business Set-Aside opportunity involves furnishing and installing a new two-span box beam bridge system, including the removal of the existing structure and extensive environmental protection measures. The estimated magnitude for this project is between $1,000,000 and $5,000,000. Bids are due by May 21, 2026, at 10:30 AM ET.
Scope of Work
The project requires comprehensive construction services for a new two-span box beam bridge on FR 135 over the Williams River. Key tasks include:
- Construction survey and staking, clearing and grubbing.
- Installation of cofferdams, dewatering, and excavation for riprap.
- Removal of the existing bridge structure and installation of the new bridge.
- Micro piling design and installation, roadway subbase, aggregate, asphalt, guardrail, and riprap armoring.
- Extensive environmental protection, including Erosion and Sediment (E&S) control, turbidity monitoring, in-channel perimeter control, fish relocation (specifically candy darter monitoring and capturing), and stream rehabilitation.
- The contractor must furnish all necessary personnel, material, equipment, and services. In-stream work is restricted to July-October.
Contract Details
- Contract Type: Invitation for Bids (IFB), Firm Fixed Price (FFP)
- Set-Aside: Total Small Business Set-Aside
- NAICS Code: 237310 - Highway, Street, and Bridge Construction (Size Standard: $45,000,000)
- Estimated Magnitude: $1,000,000 - $5,000,000
- Period of Performance: May 4, 2026 – November 30, 2027 (310 business days), with a winter shutdown period from December 1, 2026 – March 30, 2027.
Submission & Evaluation
- Submission Method: Bids must be emailed to Kevin.Brown2@usda.gov.
- Bid Requirements: Include Attachment 1 Schedule of Items (priced) and acknowledge all amendments. A bid bond (Standard Form 24) is required for bids exceeding $150,000.
- Evaluation: Award will be made to the lowest priced, responsible bidder.
- Public Bid Opening: A public bid opening will be held via Microsoft Teams on May 21, 2026, at 10:30 AM ET.
Key Dates & Amendments
- Questions Due: May 18, 2026, 12:00 PM ET.
- Bids Due: May 21, 2026, 10:30 AM ET (extended by Amendment 0001).
- Amendment 0003 added a Vendor Q&A document.
- Amendment 0002 added Attachment 11, the Subsurface Investigation Report.
Important Attachments / Notes
Bidders are strongly encouraged to inspect the location before bidding. Critical documents to review include the Statement of Work (Attachment 2), detailed Plans (Attachment 3), extensive Supplemental Specifications (Attachment 4) which revise numerous sections, Conservation Measures (Attachment 6), Turbidity Monitoring Plan (Attachment 7), Subsurface Investigation Report (Attachment 11), Wage Determination (Attachment 10), and the Vendor Q&A document. These documents provide crucial details on technical requirements, environmental compliance, geotechnical conditions, and prevailing wage rates.