Y--Montezuma NWR New Multipurpose Facility
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The U.S. Fish and Wildlife Service (FWS), under the Department of the Interior, has issued a Solicitation (140FGA26R0006) for the construction of a New Multipurpose Facility at the Montezuma National Wildlife Refuge (NWR) and NY Ecological Services. This opportunity is a Total Small Business Set-Aside (FAR 19.5) for construction of office buildings (PSC Y1AA). Proposals are due April 20, 2026, at 1400 local time.
Scope of Work
The project involves the construction of a base building multipurpose facility. Key requirements include:
- Base Building Multi-Purpose Facility Construction.
- Additive #1: Resurfacing of the shaded pavement area and additional sidewalks (Drawing C-102).
- Additive #2: PV system on the South Roof.
- Additive #3: PV system on the North Roof.
- Additive #4: Furniture for the facility. Clarifications confirm power and data receptacles for tabletops in Room 104, and specific finish material grades/colors will be identified. CAD files will be provided post-award for shop drawing preparation.
Contract & Timeline
- Type: Solicitation (Proposals will be evaluated, not an Invitation for Bid).
- Set-Aside: Total Small Business Set-Aside (FAR 19.5).
- Performance Period: June 1, 2026, to November 30, 2027 (548 calendar days after Notice to Proceed).
- Proposal Due: April 20, 2026, at 1400 local time.
- Question Deadline: April 3, 2026, at 2:00 PM Eastern Time (as extended by Amendment 0002).
- Bonds: Performance and payment bonds are required.
- Funding: Obligation is contingent upon the availability of appropriated funds.
Key Clarifications & Requirements
Recent amendments and Q&A documents provide crucial details:
- Geotechnical Reports: Two detailed geotechnical reports (2303568_FINAL_MNWR_Geotech_Report_R1-Nov2024 and 21003122A_-Montezuma_NWR-_Geotechnical_Report_Sealed) were provided with Amendment 0001, critical for foundation design and construction planning.
- Site Specifics: Water line extension terminates at a valve/cap by others. Exterior fence details require reconciliation between architectural and civil drawings. Coordination with the Refuge Manager for wetland drawdown is possible.
- Specifications: The "Regional Materials" provision in Rough Carpentry Specification (06 10 00-2) has been deleted, removing regional materials or certified wood criteria.
- MWBE Goals: The rescission of Executive Order 11246 means there are no mandated MWBE contracting goals.
Submission & Contact
Offers must be submitted in original and one copy, sealed and marked with offeror's name, address, solicitation number, and offer due date/time. Offers providing less than 60 calendar days for Government acceptance will be rejected. All questions must be submitted via email to Ian Young (ian_a_young@fws.gov).