Morganza to the Gulf Hurricane and Storm Damage Reduction Project Sources Sought – Commercial Clay Borrow Source

SOL #: W912P826SS0008Sources Sought

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W07V ENDIST NEW ORLEANS
NEW ORLEANS, LA, 70118-3651, United States

Place of Performance

Place of performance not available

NAICS

No NAICS code specified

PSC

No PSC code specified

Set Aside

No set aside specified

Timeline

1
Posted
Apr 22, 2026
2
Response Deadline
Aug 20, 2026, 4:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers (USACE), New Orleans District, is conducting a Sources Sought to identify potential commercial clay borrow sources for the Mississippi River and Tributaries, Morganza to the Gulf (MTG) Project in Terrebonne and Lafourche Parishes, Louisiana. The primary goal is to establish a pre-approved list of sources that can supply approximately 54,000,000 cubic yards of clay borrow material for various construction contracts associated with the MTG Project. This is not a solicitation for construction services. Responses are due by August 20, 2026, at 11:00 AM local time.

Scope of Need

USACE seeks to identify and pre-qualify commercial borrow pits capable of providing significant quantities of clay material. The MTG Project involves ongoing construction with a goal to have all construction underway by 2035, requiring a substantial and reliable supply of clay. Inclusion on the pre-qualified list will enable sources to be considered for future solicitations, though it does not guarantee work.

Key Requirements for Sources

Interested entities must provide comprehensive information, including:

  • Firm name, address, phone, and point of contact.
  • A Statement of Capability detailing skills, experience, knowledge, and equipment relevant to supplying clay borrow material.
  • A valid CAGE Code and DUNS number.
  • All requirements listed in Appendix A, which must be current and updated within the last 12 months. Appendix A mandates detailed documentation such as:
    • Certificate of Good Standing from Louisiana Secretary of State.
    • Appropriate state and local permits.
    • Right of Entry for Investigations document.
    • Maps detailing access, topography, and excavation layout.
    • Wetland Delineation Report or Jurisdictional Determination.
    • Confirmation of Non-jurisdictional Wetlands.
    • Coastal Zone Management (CZM) permit or letter.
    • Threatened & Endangered Species (T&E) report and concurrence.
    • Cultural Resource Survey Report.
    • Environmental Site Assessment (ESA).
    • Geotechnical Report with Soil Boring Analysis and Laboratory Tests.
    • Levee District Letter of No Objection/Permit (if applicable).
    • Borrow Area Management Plan.
    • Avoidance, Minimization and Mitigation Requirements plan.
    • Zoning Classification evidence.
    • Environmental Protection Plan.

Submission Details

Responses must be received on or before August 20, 2026, at 11:00 AM local time. Submissions should be sent via email to Taylor.H.Brandon@usace.army.mil. For large files, respondents should email the same address to request access to DoD SAFE for submission. Early submissions are encouraged, as feedback may be provided, potentially requiring further actions on submitted materials.

Contract & Timeline

  • Opportunity Type: Sources Sought
  • Department/Agency: Department of Defense / Department of the Army / USACE New Orleans District
  • Project: Morganza to the Gulf (MTG) Hurricane and Storm Damage Reduction Project
  • Estimated Material Need: Approximately 54,000,000 cubic yards of clay borrow material.
  • Project Timeline: Construction is ongoing, with a goal to have all construction underway by 2035.
  • Response Due: August 20, 2026, 11:00 AM local time.
  • Published: April 22, 2026.
  • Set-Aside: None specified.

People

Points of Contact

Taylor H. BrandonPRIMARY
Christopher NuccioSECONDARY

Files

Files

Download

Versions

Version 1Viewing
Sources Sought
Posted: Apr 22, 2026
Morganza to the Gulf Hurricane and Storm Damage Reduction Project Sources Sought – Commercial Clay Borrow Source | GovScope