N442487477134 P990 Abandoned Piping Demo

SOL #: N442487477134Solicitation

Overview

Buyer

Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM MID-ATLANTIC
NORFOLK, VA, 23511-0395, United States

Place of Performance

Cherry Point, NC

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Construction Of Miscellaneous Buildings (Y1JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Dec 10, 2025
2
Last Updated
Apr 3, 2026
3
Submission Deadline
Jan 7, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Navy / NAVFACSYSCOM MID-ATLANTIC is soliciting proposals for the P990 Abandoned Piping Demo project at Marine Corps Air Station (MCAS) Cherry Point, North Carolina. This project involves the removal of abandoned utility pipes to establish a Duke Energy Corporation right of way. This is a Total Small Business Set-Aside opportunity, open only to MACC holders. Proposals are due January 7, 2026, at 2:00 PM EST.

Scope of Work

The work includes the removal of various abandoned utility pipes (e.g., DI water, DI sanitary, PVC forced sanitary, STL gas, fire/security/communication conduits) within the designated path. Key tasks involve:

  • Field verification of existing utility locations and depths using Ground Penetrating Radar (GPR) or electromagnetic/sonic equipment prior to excavation.
  • Hand or soft digging around abandoned pipes and avoiding existing underground electrical utilities.
  • Locating and capping pipes at easement boundaries.
  • Backfilling and compacting the abandoned pipe trenches.
  • Adherence to stringent governmental safety requirements, including the use of Personal Protective Equipment (PPE), Accident Prevention Plans, and Activity Hazard Analysis.
  • Compliance with MCAS Cherry Point and FRC East regulations, including identification badge requirements (DBIDS), "No Smoking" policy, and Foreign Object Debris (FOD) prevention measures.
  • Environmental protection requirements, waste management, stormwater controls, and air pollution prevention.

Contract & Timeline

  • Contract Type: Solicitation (Implied Firm Fixed-Price based on Lowest Price award and Liquidated Damages)
  • Estimated Value: Between $250,000 and $500,000
  • Contract Duration: 45 calendar days after award
  • Liquidated Damages: $800 per calendar day of delay
  • Bond Requirements: Bid bonds for proposals $150K and greater; Payment bonds for proposals $35K and greater. Bonds must be provided electronically with visible SEALS.
  • Proposal Due Date: January 7, 2026, 2:00 PM EST
  • RFI Cut-off Date: 23 December 2025, 2:00 PM EST
  • NAICS Code: 238220 (Plumbing, Heating, and Air-Conditioning Contractors)

Eligibility & Evaluation

  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • Eligibility: Only MACC holders listed on the first page of the solicitation may submit a proposal.
  • Basis for Award: Lowest Price. The Government intends to evaluate proposals and issue a task order without discussions.

Key Documents & Submission

  • Mandatory Documents: Refer to Specification Section 01 35 26 for SSHO and Superintendent roles/qualifications, and Section 31 00 00 for earthwork and revegetation scope. Site plans (e.g., 12913286_REV1.pdf, 7477134 DWGSASONE.pdf) detail demolition work.
  • Submission: Proposals and RFIs must be submitted via email to sarah.a.shugart.civ@us.navy.mil and usn.cherrypoint.navfacmidlandnor.mbx.FEAD-CP-Proposals@us.navy.mil.
  • Acknowledgement: Vendors must acknowledge Amendment 0002 with their proposal.

People

Files

Files

Download
Download
Download
Download
Download

Versions

Version 3
Solicitation
Posted: Apr 3, 2026
View
Version 2
Solicitation
Posted: Dec 31, 2025
View
Version 1Viewing
Solicitation
Posted: Dec 10, 2025