Pendleton Building Repairs Project E (Adams, OR)

SOL #: 1232SA26Q0209Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Agricultural Research Service
USDA ARS AFM APD
BELTSVILLE, MD, 20705, United States

Place of Performance

Adams, OR

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Construction Of Miscellaneous Buildings (Y1JZ)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Feb 25, 2026
2
Last Updated
Mar 26, 2026
3
Submission Deadline
Apr 8, 2026, 7:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The United States Department of Agriculture (USDA), Agricultural Research Service (ARS) is soliciting quotations for the Pendleton Building Repairs Project E at the Columbia Plateau Conservation Research Center in Adams, OR. This Total Small Business Set-Aside opportunity requires comprehensive building repairs, including HVAC system modifications for new fume hoods. The estimated Rough Order of Magnitude (ROM) for the Base Bid is between $100,000 and $250,000, with the Base Bid combined with an Alternate estimated between $250,000 and $500,000. Quotations are due by April 8, 2026.

Scope of Work

This project involves providing all labor, supervision, tools, and materials for building repairs as detailed in the attached scope documents, specifications, and drawings. Key aspects include:

  • Base Bid: Installation of an exhaust system for a 6ft fume hood in Room 306, supplemental heating/cooling, electrical connections, and exterior structural platform design.
  • Alternate 01: Installation of a fume hood and exhaust system in Room 312, electrical connections, and exterior structural platform design.
  • Work must adhere to detailed technical specifications (Attachment 2) and architectural drawings (Attachment 3).

Contract & Timeline

  • Contract Type: Request for Quotation (RFQ) leading to an anticipated Firm Fixed Price contract.
  • Period of Performance: 360 days from the Notice to Proceed.
  • Set-Aside: Total Small Business Set-Aside (NAICS 236220, size standard $45M).
  • Response Due: April 8, 2026, 7:00 p.m. UTC.
  • Published Date: March 26, 2026 (latest amendment).

Submission & Evaluation

Offerors must submit quotations via email to Spencer Hamilton (spencer.hamilton@usda.gov). Submissions must include company letterhead, pricing, SAM UEI, acknowledgement of all amendments, active SAM.gov registration, and completed electronic representations and certifications.

  • Evaluation Criteria: Lowest Price Technically Acceptable (LPTA). Technical acceptability will be rated "acceptable" or "unacceptable" based on Technical Experience and Past Performance. Price will be evaluated for fairness and reasonableness.
  • Offer Acceptance Period: Prices must be held firm for 90 calendar days.
  • Bonding: Bid guarantees are required for proposals over $150,000, and payment/performance bonds for awards over $35,000.

Key Clarifications (from Amendment 0002 Q&A)

  • Rough Order of Magnitude (ROM): Base Bid $100K-$250K; Base Bid + Alternate $250K-$500K.
  • Liquidated Damages: None associated with this project.
  • Permits: No permits are required for the work.
  • Structural Engineering: The awarded contractor is responsible for providing stamped shop drawings and calculations for the HVAC support structure and foundation, utilizing preliminary designs provided.
  • Special Inspections: The contractor is responsible for hiring and paying for special inspections.
  • Personnel: One qualified individual can fulfill SSHO, QC, and Superintendent roles if they meet all qualifications.
  • Duct Material: PVC ductwork for fume hoods (spec 233116); Stainless steel for connections to EF-003-03 (spec 233100).

Important Dates

  • Site Visit: March 19, 2026 (past).
  • Questions Deadline: March 25, 2026, 12:00 p.m. Pacific Time (past).

Contact

For inquiries, contact Spencer Hamilton at spencer.hamilton@usda.gov.

People

Points of Contact

Spencer HamiltonPRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 3Viewing
Combined Synopsis/Solicitation
Posted: Mar 26, 2026
Version 2
Combined Synopsis/Solicitation
Posted: Mar 19, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Feb 25, 2026
View
Pendleton Building Repairs Project E (Adams, OR) | GovScope