Reline Fire Water Storage Tank 558
SOL #: N4008526R0021Combined Synopsis/Solicitation
Overview
Buyer
Dept Of Defense
Dept Of The Navy
NAVFACSYSCOM MID-ATLANTIC
NORFOLK, VA, 23511-0395, United States
Place of Performance
Colts Neck, NJ
NAICS
Electroplating (332813)
PSC
Repair Or Alteration Of Water Supply Facilities (Z2NE)
Set Aside
Total Small Business Set-Aside (FAR 19.5) (SBA)
Original Source
Timeline
1
Posted
Mar 20, 2026
2
Last Updated
May 14, 2026
3
Submission Deadline
May 15, 2026, 3:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Navy, specifically NAVFACSYSCOM MID-ATLANTIC, is soliciting proposals for construction services to Reline Fire Water Storage Tank 558 at Naval Weapons Station Earle in Colts Neck and Leonardo, New Jersey. This is a Total Small Business Set-Aside opportunity. The project involves comprehensive relining, surface preparation, and painting of the 300,000-gallon fire water tank. Proposals are due June 17, 2026, by 1100 EST.
Scope of Work
The primary objective is to repaint the interior and exterior of Tank 558. This includes:
- Removal of all existing paint via media blasting with full containment.
- Preparation of exposed steel surfaces to meet specified profile requirements.
- Application of a new three-coat paint system to interior and exterior surfaces, including all previously painted exterior items.
- Treatment and disposal of all paint and abrasive blast material as hazardous waste.
- Pit welding for pitting at least 1/4 inch deep and filling rough-edged pitting with solventless epoxy seam sealer.
- Contractor responsibility for testing the cathodic protection system before and after work, and fixing it if not working properly (per NACE SP0193-2016).
- Contractor responsibility for removing residual water after the Government drains the tank.
- Replacement of the existing roof vent with a clog-resistant vent (AWWA D100-11 Sec 7.5).
- Replacement of the existing stub overflow pipe with a new pipe (AWWA D100-11 Sec 7.3).
- Protection of existing structures and surrounding areas from damage.
Contract Details
- Contract Type: Firm Fixed Price (FFP)
- Magnitude: Estimated between $1,000,000 and $5,000,000.
- Period of Performance: 120 calendar days from Notice to Proceed.
- Liquidated Damages: $857.72 per calendar day.
- Bonds: Performance, Payment, and Bid Guarantees are required.
- Offer Validity: 60 days.
Eligibility & Set-Aside
- This is a 100% Total Small Business Set-Aside (FAR 19.502-2).
- Contractors must be registered in SAM.gov and comply with military base access requirements.
Submission & Evaluation
- Proposal Due Date: June 17, 2026, NLT 1100 EST.
- Submission Method: Electronically.
- Basis for Award: Lowest Price Technically Acceptable (LPTA).
- Evaluation Factors: Price, Corporate Experience, and Past Performance.
- Site Visit: A site visit was held on April 7, 2026.
Key Updates
- Amendment 0002 (May 14, 2026) extended the proposal due date to June 17, 2026.
- Amendment 0001 (April 22, 2026) provided updated red-lined specifications and drawings, and previously extended RFI and proposal due dates.
- Subsequent amendments clarified contractor responsibilities for cathodic protection testing, residual water removal, and replacement of the roof vent and overflow pipe.
Contact Information
- Primary: Jessica Mercurio, jessica.a.mercurio.civ@us.navy.mil, 732-866-2825
- Secondary: Joseph Henrius, joseph.p.henrius.civ@us.navy.mil, 732-866-2152
People
Points of Contact
Jessica MercurioPRIMARY
Joseph HenriusSECONDARY
Files
Versions
Version 5Viewing
Combined Synopsis/Solicitation
Posted: May 14, 2026
Version 4
Combined Synopsis/Solicitation
Posted: May 11, 2026
Version 3
Combined Synopsis/Solicitation
Posted: Apr 22, 2026
Version 2
Combined Synopsis/Solicitation
Posted: Apr 2, 2026
Version 1
Combined Synopsis/Solicitation
Posted: Mar 20, 2026