B755 EIFS & Door Repair
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force has awarded a Firm Fixed-Price contract for B755 EIFS & Door Repair at the Minneapolis Air Reserve Station, MN. The contract, valued at $157,900.00, was awarded to QLC Solutions Inc. for comprehensive repairs to the Base Exchange (Building 755).
Scope of Work
The awarded contractor, QLC Solutions Inc., will perform repairs including:
- Exterior Insulation and Finish System (EIFS) Repair: Addressing cracks, holes, voids, and joints, followed by a new finish coat.
- Door Repair and Replacement: Replacing main entrance door operators, sensors, and controls; brick infill for one double door; and replacing a single door, frame, hardware, and accessories.
- Sign Relocation: Removing an existing sign and exterior conduit, then mounting a new sign in a designated location.
- Conduit Rerouting: Removing exterior tank level alarm conduit and rerouting new conduit to the interior of the facility.
- General construction debris removal and site restoration.
Contract Details
- Contract Type: Firm Fixed Price (FFP)
- Award Value: $157,900.00
- Awarded To: QLC Solutions Inc.
- Set-Aside: 100% Small Business Set-Aside
- NAICS Code: 236220 (Commercial and Institutional Building Construction)
- Period of Performance: Work to begin within 10 calendar days of award and be completed within 120 calendar days of the Notice to Proceed.
- Place of Performance: Minneapolis Air Reserve Station, Minneapolis, MN.
Evaluation
The original solicitation was evaluated on a price-related factor basis, with the award made to the lowest-priced responsible offeror whose quote was responsive and deemed best value.
Additional Notes
The project requires adherence to detailed specifications, drawings, and a Statement of Work. Performance and Payment Bonds were required. The solicitation process included a site visit and multiple amendments, with the final offer due date being April 30, 2026.