Request for Proposals - Central Utility Building Purge Unit Replacement for Chiller No. 5 Fermi National Accelerator Laboratory, Batavia, Illinois

SOL #: RFP380663CJSolicitation

Overview

Buyer

Energy
Energy, Department Of
FERMILAB - DOE CONTRACTOR
Batavia, IL, 60510, United States

Place of Performance

Batavia, IL

NAICS

Plumbing (238220)

PSC

Maintenance, Repair And Rebuilding Of Equipment: Refrigeration, Air Conditioning, And Air Circulating Equipment (J041)

Set Aside

No set aside specified

Timeline

1
Posted
May 15, 2026
2
Submission Deadline
Jun 12, 2026, 5:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Fermi National Accelerator Laboratory (Fermilab), through Fermi Forward Discovery Group, LLC (FFDG), is soliciting proposals for the replacement of the purge unit for Chiller No. 5 at its Central Utility Building (CUB) in Batavia, Illinois. This effort involves removing, replacing, testing, and returning the chiller to operational condition. The contract type is Time and Material (T&M) / Labor Hour. Proposals are due by June 5, 2026, 12:00 p.m. CT.

Scope of Work

The selected subcontractor will provide all necessary labor, supervision, management, materials, tools, equipment, and transportation. The work includes: removal of the existing purge unit and associated piping, installation of a new purge unit and piping, integration with Chiller No. 5 control systems, system evacuation, leak testing, refrigerant recharge, and startup. All work must comply with federal, state, and local regulations, Fermilab site-specific safety procedures (including LOTO and refrigerant handling), and manufacturer specifications.

Contract & Timeline

  • Contract Type: Time and Material (T&M) / Labor Hour.
  • Anticipated Start Date: June 10, 2026.
  • Place of Performance: Central Utility Building, Fermilab, Batavia, IL.
  • Set-Aside: None specified.
  • Proposal Due Date: June 5, 2026, 12:00 p.m. (CT).
  • Published Date: May 15, 2026.

Key Requirements & Eligibility

  • Offerors must be Trane-certified and capable of procuring Original Equipment Manufacturer (OEM) parts.
  • Demonstrated experience servicing Trane chillers of similar size, complexity, and configuration.
  • Submission of a Corporate Quality Control Plan (guidance provided in Attachment H).
  • Submission of safety documentation demonstrating acceptable safety performance (Attachment G outlines ES&H requirements).
  • Copies of all valid and current HVAC/chiller maintenance and repair licenses and permits.
  • Compliance with Wage Determination (Illinois Kane SCA 2015-5741, Rev. 27).
  • Adherence to specific insurance requirements (General Liability, Automobile Liability, Excess/Umbrella Liability, Workers' Compensation, Employer's Liability) as detailed in Attachment D.
  • Completion of FFDG Proposal Certifications (Attachment F) and Subcontractor Annual Representations & Certifications (SARC) (Attachment E).

Evaluation

Award will be made using a Lowest Price Technically Acceptable (LPTA) source selection method. Technical and Past Performance factors will be evaluated on an acceptable/unacceptable basis. The award will go to the offeror submitting the lowest evaluated price whose proposal is technically acceptable.

Submission & Attachments

Proposals must be submitted in three parts: Technical Proposal, Pricing Schedule/Representations/Certifications, and Past Performance. An optional site visit is scheduled for June 2, 2026, from 10:00 a.m. to 11:30 a.m. (CT) at Fermilab. Questions regarding the RFP must be submitted in writing via email by June 5, 2026, 12:00 p.m. (CT). Key attachments include the Statement of Work (A), Pricing Schedule (B), T&M Terms & Conditions (C), Insurance Requirements (D), SARC (E), Proposal Certifications (F), Safety (G), Quality Requirements (H), and Wage Determination (I).

Contact Information

People

Points of Contact

Caroline JonesPRIMARY
Latasha JohnsonSECONDARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 1Viewing
Solicitation
Posted: May 15, 2026
Request for Proposals - Central Utility Building Purge Unit Replacement for Chiller No. 5 Fermi National Accelerator Laboratory, Batavia, Illinois | GovScope