Sam Houston Trail Bridge Replacement
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service, Southwestern Regional Office, Region 3, is soliciting proposals for the Design-Build construction of approximately 18 replacement trail bridges on the Multi-Use Trail (MUT) within the Sam Houston National Forest, west of New Waverly, TX. This project addresses failed or failing bridges due to storm events and erosion. The estimated magnitude of construction is between $1,000,000 and $5,000,000. This is a Total Small Business Set-Aside. Proposals are due April 17, 2026.
Scope of Work
The project encompasses all labor, materials, equipment, supplies, travel, supervision, and incidentals for the full design and construction of the bridges. Key phases include:
- Phase A: Site Investigation and Analysis.
- Phase B: Design and Construction Document Preparation.
- Phase C: Removal and disposal of existing crossing infrastructure, construction of new crossings, and connecting trail approaches.
Bridges require a minimum deck width of 72 inches, increased spans, and freeboard. Design considerations include modular/field-constructable designs, elevated boardwalk structures for shallow streams, and tread hardening, meeting a minimum 500-year storm interval with 30% debris blocking and 18" freeboard.
Contract & Timeline
- Contract Type: Firm-fixed-price Design-Build construction contract.
- Set-Aside: Total Small Business Set-Aside (FAR 19.5).
- NAICS Code: 237310 – Highway, Street, and Bridge construction (Small Business Size Standard: $45 million).
- Estimated Magnitude: $1,000,000 - $5,000,000.
- Period of Performance: 390 calendar days after receipt of Notice to Proceed (NTP).
- Questions Due: April 2, 2026.
- Site Visit: Strongly encouraged. Scheduled for Friday, April 3, 2026, at 9:00 AM Central Time at the Sam Houston National Forest Ranger Station, 394 FM 1375 West, New Waverly, TX 77358.
- Proposals Due: April 17, 2026, at 1300 local time.
- Published Date: March 26, 2026.
Submission & Evaluation
Proposals must be submitted electronically to david.l.watson@usda.gov and organized into two volumes: Technical Proposal and Price Proposal. Evaluation will be based on a Best Value Tradeoff process, considering Technical Approach, Relevant Experience, Key Personnel (Project Manager, Design Engineer, Construction Superintendent), Past Performance, and Price. Non-price factors combined are approximately equal to price.
Additional Notes
Offerors are strongly encouraged to visit the project site. Performance and payment bonds (100% of contract price) are required within 10 calendar days after receipt of the notice of award. The solicitation incorporates various Federal Acquisition Regulation (FAR) and USDA Acquisition Regulation (AGAR) clauses, including FAR 52.223-23 Sustainable Products and Services (MAY 2024) (DEVIATION FEB 2025).