SSRL B116 & B132 BPM HVAC Replacement
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Energy (DOE), through SLAC National Accelerator Laboratory, has issued a Request for Proposal (RFP) #363431 for the SSRL B116 & B132 BPM HVAC Replacement Project. This opportunity seeks a qualified subcontractor to remove and replace HVAC systems in critical Beam Position Monitor (BPM) Rooms. Proposals are due April 30, 2026, at 10:00 AM PST.
Scope of Work
The project involves the complete demolition and replacement of existing HVAC systems in Buildings 116 and 132 at SLAC SSRL. This includes installing modern, like-for-like replacements such as new Vertiv Liebert HVAC equipment, ductwork, refrigeration piping, condensate lines, and associated electrical infrastructure. The primary objective is to maintain critical temperature stability for SPEAR equipment. Work also includes providing concrete housekeeping pads, bollards, field surveys, temporary facilities, dust and environmental controls, and protecting existing materials.
Contract & Timeline
- Contract Type: Firm Fixed Price Subcontract
- Period of Performance: Work is primarily scheduled during SSRL's Summer 2026 shutdown, from July 21, 2026, through September 15, 2026, with the HVAC system required to be operational by September 19, 2026. A potential Phase 2 for remaining work may occur during the Summer 2027 shutdown (July-September 2027) if equipment lead times impact full 2026 completion.
- Set-Aside: None specified.
- Proposal Due: April 30, 2026, 10:00 AM PST
- Site Visit: April 6, 2026, 10:00 AM PST (strongly recommended, meet Building 53). Attendee list due April 2, 2026.
- Questions (RFIs) Due: April 23, 2026 (COB), submitted via the provided Question & Answer Log.
Evaluation & Eligibility
Award will be made on a lowest-price, technically acceptable basis. Proposals will be evaluated on:
- Technical Approach: Understanding of scope, project planning, QA/QC, assumptions.
- Safety: ES&H program, environmental compliance, safety history (EMR/OSHA 300 logs). A valid Safety Qualification Form is required.
- Schedule & Phasing Plan: Adherence to summer downtime completion goals.
- Project Management & Experience: Methodologies, key personnel qualifications (OSHA 30 minimum for Site Safety Representative), relevant past projects.
- Statement of Qualifications: Valid California contractor's license, local San Francisco Bay Area office (3+ years established), experience with DOE National Laboratories or similar facilities. Offerors must be registered in SAM and the University's procurement system.
Key Requirements & Notes
This is a federally funded construction project subject to the Davis-Bacon Act and DOE WH Publication 1321, requiring weekly certified payroll reports via SLAC's LCPtracker software. Subcontractors must submit an Injury and Illness Prevention Plan (IIPP) Acknowledgement Form with their proposal. Pre-award requirements for Notice to Proceed include performance/payment bonds and various insurance certificates. All communications must be directed to the Senior Subcontract Administrator, Doreen Agbayani.