Tinker AFB MACBOA WWYK250172 Replace Walls of Iszard Pool
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force is soliciting proposals for WWYK250172 – Replace Walls of Iszard Pool House at Tinker Air Force Base, Oklahoma. This Total Small Business Set-Aside opportunity, valued between $500,000 and $1,000,000, is exclusively for Tinker AFB - MAC BOA Holders. A mandatory initial site visit was held on March 25, 2026, and attendance was required for eligibility. Proposals are due by June 15, 2026, at 03:00 PM local time.
Scope of Work
This project involves furnishing all materials, labor, and equipment to replace CMU fence walls, the roof, and electrical systems & components, as well as repairing the pool house structure at Building B5730. Key tasks include:
- Demolition of existing masonry, wood fences, and roof system.
- Installation of new 8-foot metal panel fences, utility gates, and concrete sidewalks.
- Structural work, including footing details, wall bracing, and CMU control joints.
- Installation of a new PVC roof system with insulation, flashing, and drainage.
- Upgrade of electrical systems, including new lighting, panelboards, and receptacles.
- Performing a site investigation to verify existing conditions and providing all necessary logistical, architectural, and structural work elements for a complete, fully operating system.
Contract Details
- Contract Type: Firm Fixed Price Solicitation (FA813726R0016).
- Estimated Value: $500,000 to $1,000,000.
- Period of Performance: Begin within 10 calendar days and complete within 180 calendar days after Notice to Proceed (NTP).
- Bonds: Performance and Payment Bonds are required.
- Funding: Obligation is contingent upon the availability of appropriated funds.
- Place of Performance: Tinker Air Force Base, B5730, Oklahoma.
Eligibility & Submission
- Eligibility: Restricted to Tinker AFB - MAC BOA Holders ONLY. Offerors must have attended the initial site visit on March 25, 2026, to be considered eligible.
- Proposal Due Date: June 15, 2026, at 03:00 PM local time.
- Offer Validity: Proposals must be valid for at least 120 calendar days.
- Document Access: Project-specific documents are attached. For access difficulties, email Contracting Points of Contact for a DoD Safe transmission (Prime Contractor emails only).
- Key Personnel: Resumes for Project Manager, Quality Control Manager, Site Safety and Health Officer, and Project Superintendent are required within five (5) calendar days after NTP.
Evaluation & Special Requirements
- Evaluation: Instructions to Offerors and Evaluation Factors for Award are detailed in Sections L and M of the solicitation.
- Wage Determination: Compliance with General Decision Number OK20260049 for building construction in Oklahoma County is mandatory.
- Submittals: A comprehensive Submittal Register (ATT10) outlines all required documentation, including a baseline construction schedule within 10 days of NTP. Anticipated turnaround time for submittals is approximately 10 working days.
- Utilities: Contractors are responsible for identifying and protecting active utilities; hydro-excavation is preferred.
- Environmental: Asbestos-containing materials (ACM) have been identified in roofing sealant.