USDA Forest Service Lake Wedington Waterline Construction, ARKANSAS

SOL #: 12445126b0010Solicitation

Overview

Buyer

Agriculture
Forest Service
USDA-FS, CSA EAST 11
Atlanta, GA, 303092449, United States

Place of Performance

Fayetteville, AR

NAICS

Water and Sewer Line and Related Structures Construction (237110)

PSC

Repair Or Alteration Of Water Supply Facilities (Z2NE)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Mar 18, 2026
2
Last Updated
Mar 24, 2026
3
Submission Deadline
Apr 24, 2026, 3:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The USDA Forest Service is soliciting bids for the Lake Wedington Waterline Construction project in Fayetteville, Arkansas. This Invitation for Bid (IFB) is a Total Small Business Set-Aside for a firm-fixed-price contract to replace existing distribution lines and install a new potable water supply line. The project magnitude is estimated between $1,000,000 and $2,000,000. Bids are due April 24, 2026, at 1000 CT.

Project Scope

This project involves two main packages at the Lake Wedington Recreation Area:

  • Package 001 (Distribution System): Complete replacement of existing distribution lines and valves. This includes installing approximately 16,000 linear feet of waterline (1-inch to 6-inch) from the existing 22,000-gallon water storage tank to the day-use area and campground.
  • Package 002 (Supply System): Installation of approximately 6,000 linear feet of 3-inch potable waterline from Krie Road to the existing 22,000-gallon water storage tank.

Key engineering clarifications from Amendment 003 and the Q&A document include requirements for 2"-8" Schedule 40 PVC sleeving, specific pipe backfill (aggregate for paved areas, select native for others), open-cut trenching and asphalt replacement for asphalt crossings, and burying lines a minimum of 5 feet deep at creek crossings. Excess soils and brush must be removed from government property.

Contract Details & Set-Aside

  • Contract Type: Firm-Fixed Price Invitation for Bid (IFB).
  • Magnitude: $1,000,000 - $2,000,000.
  • Set-Aside: Total Small Business Set-Aside.
  • NAICS Code: 237110 - Water and Sewer Line and Related Structures Construction, with a $45 million size standard.
  • Period of Performance: 270 days after award, with completion no later than January 29, 2027.
  • Bonds: 100% Performance and Payment Bonds, and a Bid Guarantee are required.

Key Dates & Submission

  • Site Visit: March 10, 2026, 1000 CT at Lake Wedington Rec Area entrance gate. RSVP by March 7, 2026, to Danny Sims (danny.sims@usda.gov, 479-223-2176). Attendance was highly encouraged.
  • Questions Deadline: March 27, 2026. Questions were to be submitted via email.
  • Bids Deadline: April 24, 2026, 1000 CT. Email bids to steven.alves@usda.gov (cc: adam.doyle@usda.gov) with subject "12445126B0010 BID_Co. Name". Bidders must call the Contracting Officer/Contracting Specialist to confirm receipt.
  • Offer Acceptance Period: 90 calendar days from bid receipt date.

Evaluation

Award will be based on the lowest price, responsive, and responsible bid. Offerors must acknowledge all amendments (including the latest Amendment 003) on the SF30 and SF1442, and return the revised Schedule B for the Distribution System with their bid.

People

Points of Contact

Steven J AlvesPRIMARY
Adam DoyleSECONDARY

Files

Files

Download
Download
Download
Download
Download

Versions

Version 2Viewing
Solicitation
Posted: Mar 24, 2026
Version 1
Solicitation
Posted: Mar 18, 2026
View
USDA Forest Service Lake Wedington Waterline Construction, ARKANSAS | GovScope