USFS - M4 Road Slide Repair
SOL #: 127EAW26Q0007Combined Synopsis/Solicitation
Overview
Buyer
Agriculture
Forest Service
USDA-FS, CSA SOUTHWEST 6
Albuquerque, NM, 871023498, United States
Place of Performance
CA
NAICS
Highway (237310)
PSC
Repair Or Alteration Of Highways/Roads/Streets/Bridges/Railways (Z2LB)
Set Aside
Total Small Business Set-Aside (FAR 19.5) (SBA)
Original Source
Timeline
1
Posted
Apr 22, 2026
2
Last Updated
May 12, 2026
3
Submission Deadline
May 21, 2026, 6:00 PM
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The USDA Forest Service is seeking quotations for M4 Road Slide Repair at the Mendocino National Forest, California. This is a Total Small Business Set-Aside combined synopsis/solicitation for commercial items. The project involves repairing a failed road section and replacing a culvert. Quotes are due May 21, 2026, at 11:00 AM Pacific Time.
Scope of Work
The project requires the repair of a roadway and replacement of an existing culvert on FSR M4. Key tasks include:
- Excavating the failed road section and removing the existing culvert.
- Constructing a new geogrid-reinforced embankment and structural base.
- Installing a new Corrugated Metal Pipe (CMP) culvert and drop inlet.
- Rebuilding and compacting the road fill and surface course, including a three-inch aggregate surface.
- Placing riprap (Class 2 & 3) for slope retention.
- Implementing and maintaining effective soil erosion control and pollution prevention plans, including erosion control blankets (seeding is not included).
- Establishing and maintaining traffic control.
- Cleaning up all project-generated trash, debris, and residue.
- Specific technical details for addressing a fill failure are provided in the updated Drawing Sheet D-2, including the use of Type III geogrid and Class 1, Type C geotextile fabric.
Contract Details
- Contract Type: Firm Fixed Price.
- Period of Performance: Work must commence within 10 calendar days after Notice to Proceed (NTP) and be completed not later than 180 calendar days after NTP, including final cleanup. Work is expected to start in June 2026.
- Estimated Magnitude: Between $100,000 and $250,000.
- Set-Aside: Total Small Business Set-Aside (NAICS 237310, size standard $45M).
- Place of Performance: Grindstone Ranger District, Mendocino National Forest, California (GPS: 39.848255, -122.758608).
Submission & Evaluation
- Quote Submission Deadline: May 21, 2026, at 11:00 AM Pacific Time, via email to Tanya.Torres@usda.gov.
- Requests for Information (RFI) Deadline: May 12, 2026, at 11:00 AM Pacific Time (now passed). RFI responses and a new drawing sheet were incorporated via Amendment A00001.
- Evaluation Criteria: Award will be made to the offeror providing the most technically advantageous solution, considering Technical Approach, Past Performance, and Price. Price must be fair and reasonable; tradeoffs will not be conducted.
- Offer Acceptance Period: Offerors must hold prices firm for 75 calendar days from the quote due date.
- Required Submittals: Include Bid Bond (required for proposals > $150,000), Performance Bond, Payment Bond, Materials Approval, Site Safety Plan, Proposed Project Schedule/Plan/Updates, and Weekly Progress Reports.
Key Requirements & Notes
- Eligibility: Offerors must have an active SAM.gov registration and an active, valid California contractor's license appropriate for road repair work.
- Site Visit: No organized site visit is scheduled; bidders are responsible for their own site inspections.
- Administrative: Mandatory use of the electronic Invoice Processing Platform (IPP) system for invoicing. A mandatory virtual post-award conference will be held within 10 days of contract award.
- Personnel: Contractor must assign a Project Manager, Project Superintendent, and Quality Control Manager. A representative or superintendent must be present at all times work is performed.
- Environmental/Safety: Adherence to a Fire Plan for the Mendocino National Forest, including specific equipment and operational limitations based on Project Activity Levels (PAL). Contractors must submit a SWPPP or alternate erosion/sediment control plan for Forest Service review and approval at least 30 days prior to use, and a dewatering plan.
- Subcontracting: The prime contractor must perform a significant portion of the work; no single subcontractor can perform > 25%, and aggregate subcontracted work must be <= 75% without authorization.
- Documents: Bidders must review all attachments, especially the updated "Replacement Drawing Sheet_D-2_Rev_April" and the "Schedule of Items" for pricing.
People
Points of Contact
Tanya TorresPRIMARY
Files
Versions
Version 2Viewing
Combined Synopsis/Solicitation
Posted: May 12, 2026
Version 1
Combined Synopsis/Solicitation
Posted: Apr 22, 2026