WA ERFO NPS OLYM 2022-1(3), OLYMPIC NPS ERFO REPAIRS 2022 Road 107

SOL #: 69056726B000006Solicitation

Overview

Buyer

Transportation
Federal Highway Administration
690567 WESTERN FEDERAL LANDS DIV
VANCOUVER, WA, 98661, United States

Place of Performance

Forks, WA

NAICS

Highway (237310)

PSC

Construction Of Highways, Roads, Streets, Bridges, And Railways (Y1LB)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Dec 9, 2025
2
Last Updated
Mar 27, 2026
3
Submission Deadline
Mar 25, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Federal Highway Administration (FHWA), Western Federal Lands Division, issued an Invitation for Bids (IFB) for Emergency Relief for Federally Owned (ERFO) Repairs on Road 107 within Olympic National Park, Jefferson County, Washington. This Total Small Business Set-Aside project involved extensive bank stabilization and roadway repairs. The Engineer's Estimate for this firm-fixed-price contract was $2,311,890.00. The bid opening occurred on March 25, 2026.

Scope of Work

The project, titled "OLYMPIC NPS ERFO REPAIRS 2022 Road 107," addresses damage from the November 2021 atmospheric river event. Key deliverables include:

  • Bank Stabilization: Installation of Class 4 and Class 5 riprap, engineered log jams (ELJ) with dolosse, root wads, log bundles, boulders, and coarse woody debris at Mile Post (MP) 0.3-0.5 and MP 0.8.
  • Environmental Elements: Planting of government-furnished species (Sitka Spruce, Sitka Willow, Cottonwood, Red Alder, Western Red Cedar), turf establishment, and temporary stream diversions.
  • Erosion Control: Implementation of fiber rolls and rolled erosion control products.
  • Roadway Work: Placement of roadway aggregate and temporary traffic control measures (e.g., flaggers, signs, pavement markings).
  • Specifics: MP 0.3 involves a 3-foot thick revetment with Class 4 riprap, root wads, and boulders. MP 0.8 includes four 80-foot ELJ units with log-dolos bundles and root wads, plus Class 5 riprap.

Contract Details

  • Type: Firm-Fixed-Price (IFB)
  • Estimated Value: Engineer's Estimate: $2,311,890.00
  • Period of Performance: Work to commence within 10 calendar days after notice to proceed (assumed by May 22, 2026), with completion not later than August 19, 2026.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5)
  • Product Service Code: Y1LB - Construction Of Highways, Roads, Streets, Bridges, And Railways

Submission & Evaluation

  • Bid Opening Date: March 25, 2026, at 2:00 p.m. local time. (Bidding is closed).
  • Submission Method: Printed bids were required; electronic bids were not accepted.
  • Evaluation: Based on price and other price-related factors.

Additional Notes

The project utilizes US Customary Units and adheres to FP-24 specifications. Technical questions were to be submitted via email to wfl.plans-spec@dot.gov. General questions were directed to wfl.contracts@dot.gov.

People

Points of Contact

Contracts G. OfficePRIMARY

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 5
Solicitation
Posted: Mar 27, 2026
View
Version 4Viewing
Solicitation
Posted: Mar 25, 2026
Version 3
Solicitation
Posted: Feb 18, 2026
View
Version 2
Solicitation
Posted: Feb 17, 2026
View
Version 1
Pre-Solicitation
Posted: Dec 9, 2025
View