White City Southern Oregon Rehabilitation Center and Clinics Seismic Upgrades

SOL #: W9127N26RA012Pre-Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W071 ENDIST PORTLAND
PORTLAND, OR, 97204-3495, United States

Place of Performance

White City, OR

NAICS

Commercial and Institutional Building Construction (236220)

PSC

Construction Of Hospitals And Infirmaries (Y1DA)

Set Aside

No set aside specified

Timeline

1
Posted
Jan 30, 2026
2
Last Updated
Apr 1, 2026
3
Response Deadline
Mar 15, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Army Corps of Engineers (USACE) Portland District is preparing a full and open pre-solicitation for a Design-Build, Firm-Fixed-Price contract for Seismic Upgrades at the VA Southern Oregon Rehabilitation Center and Clinics (SORCC) in White City, OR. This project, with a target ceiling of $260M, involves significant new construction and demolition. The solicitation is anticipated for release in the back half of 2Q 2026.

Project Overview

The scope includes the design and construction of two new buildings: B300 (Support, approximately 80,074 BGSF) and B301 (Primary & Specialty Care, approximately 96,946 BGSF). The project also encompasses three new connecting corridors, a new 188-space surface parking lot, and extensive site work. Demolition of two existing buildings and four connecting corridors (totaling approximately 62,100 GSF) is also required.

Contract Details

  • Type: Firm-Fixed-Price (FFP), Design-Build (D-B)
  • Acquisition Strategy: Unrestricted, competitively negotiated, two-phase D-B selection procedures using a Best Value Trade-Off (BVTO) method (FAR Part 15, FAR Subpart 36.3).
  • Target Ceiling Price: $260,000,000 (inclusive of design and construction)
  • Period of Performance: 45 Months
  • NAICS: 236220 "Commercial and Institutional Building Construction" (Size Standard: $45M)
  • PSC: Y1DA "Construction of Hospitals and Infirmaries"
  • Set-Aside: Full and Open Competition
  • Stipends: Anticipated $400,000 for Phase 2 offerors not selected for award.
  • Incentives: An early delivery incentive of $6,000 per day (up to 60 days) is offered.

Evaluation Factors (Two-Phase Process)

  • Phase I: Designer of Record (DOR)/Design Approach, Past Performance.
  • Phase II: Concept Design Narrative, Concept Design Drawings, Concept Schedule, Small Business Commitment Plan (SBCP), Project Labor Agreement (PLA), Cost/Price.

Key Dates

  • Phase 1 Solicitation Release: Tentative back half of 2Q 2026 (Proposals due 60 days after release).
  • Phase 2 Solicitation Release: Tentative 3Q 2026 (for down-selected firms, proposals due 120 days after release).
  • Anticipated Award: Late 2Q 2027.

Submission Requirements

  • All proposals must be submitted electronically through the PIEE Solicitation Module. Offerors must register and obtain 'Proposal Manager' and 'Proposal View Only' roles.
  • Active SAM.gov registration is mandatory.
  • CMMC Level 2 (Self) Certification is anticipated, and relevant DFARS clauses will be included in the solicitation.

Industry Engagement

  • An in-person Industry Day was held on January 22, 2026.
  • A pre-recorded presentation with more detailed information will be posted on SAM.gov the first week of February 2026.
  • A vendor list from an April 2025 virtual industry day is attached to the SAM.gov posting.

Point of Contact

Nicole Adams (Primary, Nicole.A.Adams@usace.army.mil) and Jaren Bowman (Jaren.L.Bowman@usace.army.mil). Email is the preferred method for inquiries.

People

Points of Contact

Jaren BowmanSECONDARY

Files

Files

Download
Download
Download
Download

Versions

Version 4
Solicitation
Posted: Apr 1, 2026
View
Version 3Viewing
Pre-Solicitation
Posted: Mar 23, 2026
Version 2
Pre-Solicitation
Posted: Feb 3, 2026
View
Version 1
Special Notice
Posted: Jan 30, 2026
View