Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Federal Highway Administration (FHWA), Western Federal Lands Division, is soliciting proposals for WY NP GRTE 13(1), Repair North Park Road at Milepost 15.8 within Grand Teton National Park, Wyoming. This is a Task Order Request for Proposals (TORP) issued under the Yellowstone & Grand Teton Multiple Award Task Order Contract (MATOC). Proposals are due May 5, 2026, by 4:00 p.m. local time.
Eligibility & Set-Aside
This TORP is solely for specific MATOC IDIQ holders. Only the following prime contractors are eligible to submit proposals: H-K CONTRACTORS, INC., M.A. DEATLEY CONSTRUCTION, INC., MISSOURI RIVER CONTRACTORS, LLC, OFTEDAL CONSTRUCTION, INC., RIVERSIDE CONTRACTING INC, and SUNDT CONSTRUCTION, INC. This notice is also intended to publicize subcontracting opportunities. Large businesses must submit an acceptable subcontracting plan.
Scope of Work
The project involves the repair of approximately 0.07 miles of North Park Road at Milepost 15.8. Key requirements include:
- Asphalt surface repair and deep patching
- Roadway excavation and geotechnical stabilization
- Underdrain system installation
- Clearing & grubbing, culvert removal & installation
- Temporary and permanent traffic control measures All work is governed by the "Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-24." The contractor must utilize the "Masterworks" web-based system for daily reports and measurement notes.
Contract Details
- Contract Type: Firm-fixed-price task order contract.
- Estimated Price Range: $700,000 to $2,000,000.
- Period of Performance: Work to commence within 10 calendar days after Notice to Proceed, with completion no later than September 23, 2026 (assuming NTP by July 27, 2026).
Submission & Evaluation
- Proposal Due Date: May 5, 2026, by 4:00 p.m. local time.
- Submission Method: Electronic proposals will NOT be accepted; printed copies are required.
- Offer Validity: Proposals must be valid for 60 calendar days.
- Evaluation: Award will be based on the lowest price.
Amendments & Clarifications
- Amendment A002 (April 28, 2026): Updated FAR Clause 52.244-6 and added FAR Clause 52.222-90 (Addressing DEI Discrimination).
- Amendment A001 (April 15, 2026): Modified Subsection 107.10(e) on Page E-17 and added Subsection 107.12, "Contractor's Camp," on Page E-17a.
- Latest Q&A (May 1, 2026): Clarified road access (via US 26), work hours (to limit peak travel, addressed by A001), portable traffic barriers (subsidiary obligation), traffic control (flaggers may supplement signals), and contractor campground (3 sites reserved at Flagg Ranch, addressed by A001).
Contact Information
For general inquiries, contact Contracts G. Office at wfl.contracts@dot.gov or 360-619-7520. Technical questions should be sent to wfl.plans-spec@dot.gov.