Y1LZ--Design-Build to Install Parking Shades and Reconfigure Parking Lots VAMC Las Vegas, NV Project 593-26-306
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of Veterans Affairs (VA), specifically Network Contracting Office 21 (NCO 21), is conducting market research through a Sources Sought Notice to identify qualified firms for a Design-Build project to install parking shades and reconfigure parking lots at the VA Southern Nevada Healthcare System (VAMC) in Las Vegas, NV. This is not a solicitation; responses will inform the government's acquisition strategy, including potential small business set-asides. Responses are due by June 02, 2026, at 13:00 PDT.
Project Scope
The project, identified as No. 593-26-306, requires comprehensive design-build services. The selected contractor will provide all Architect-Engineer (A/E) design services, labor, materials, equipment, supplies, investigations, and professional supervision necessary to deliver a complete solution. The primary goal is to reduce vehicle-pedestrian conflicts, enhance accessibility, and protect Veterans and staff from extreme heat. Designs must comply with OSHA, OHS, VA Master Specifications, and current applicable codes including IBC, NFPA, and OSHA.
Contract Details
- Opportunity Type: Sources Sought Notice
- NAICS Code: 236220 (Commercial building construction)
- Size Standard: $45.0M
- PSC Code: Y1LZ (Construction of Parking Facilities)
- Estimated Magnitude: Between $5,000,000.00 and $10,000,000.00
- Estimated Schedule:
- Design & Preconstruction (to 65%): ~120 calendar days from Design NTP
- Construction: ~320–340 calendar days from Construction NTP
- Total PoP (Design NTP to Final Acceptance):
515–555 calendar days (17–18.5 months)
Submission Requirements
Interested parties must submit a response via email by the deadline. The response should include:
- A Statement of Capability demonstrating experience in similar design-build projects (magnitude and scope) within the last five years for government or private entities.
- Socio-Economic Status (e.g., 8(a), SDVOSB, VOSB, Hub zone, Woman-Owned Small Business, Large Business).
- Your firm's CAGE or SAM Unique Entity Identifier (UEI) number.
- Answers to specific questions regarding the reasonableness of the period of performance, prior design-build experience with the VA or other government agencies, and bonding capability statement.
Eligibility & Notes
Potential offerors must be registered in the System for Award Management (SAM) and have a current Online Representations and Certification Application on file. Service-Disabled Veteran-Owned Small Businesses (SDVOSB) and Veteran-Owned Small Businesses (VOSB) must be VA verified and listed in the SBA Dynamic Small Business Search. This notice is for information gathering only and does not constitute a commitment to award a contract or pay for information submitted. A solicitation may be published after reviewing responses.