Buildings RR139, RR140, and RR141 Paint and Flooring Repairs
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Navy, NAVFACSYSCOM MID-ATLANTIC, is soliciting proposals for Paint and Flooring Repairs for Buildings RR139, RR140, and RR141 at MCB Camp Lejeune, NC. This is a Combined Synopsis/Solicitation under a Total Small Business Set-Aside, however, only specific M&R MACC Contractors are eligible to submit proposals. The project, identified as 25-0413, has an estimated cost range of $1,000,000 to $5,000,000. Proposals are due June 02, 2026, at 2:00 PM EST.
Scope of Work
The project involves comprehensive paint and flooring repairs across the three buildings. Key tasks include:
- Painting: Preparation, painting, and repair of all interior and exterior surfaces (walls, doors, frames, windows). This includes repairing cracks, treating mold/mildew, replacing/securing trim, and applying specific paint types per detailed specifications. Lead paint is present and requires encapsulation, not abatement.
- Flooring: Removal of existing flooring and installation of new Luxury Vinyl Tile (LVT) in sleeping rooms and Epoxy Resinous Flooring in shared/common spaces, lounges, and stairwells. This also includes surface preparation, sealing, and replacement of transition strips and cove base.
- General: Contractor is responsible for providing all material, labor, equipment, and supervision. Field verification of measurements is required. The facilities will remain operational, requiring minimal interference and special scheduling (approximately half of work areas available at a time). Contractor must move and reset furniture, potentially disassembling/reassembling.
Contract Details & Requirements
- Contract Type: Combined Synopsis/Solicitation.
- Product Service Code: Z2JZ (Repair Or Alteration Of Miscellaneous Buildings).
- Place of Performance: Camp Lejeune, NC.
- Estimated Value: $1,000,000 - $5,000,000.
- Contract Completion: 540 days after award.
- Liquidated Damages: $880 per Calendar Day.
- Bond Requirements: Bid, payment, and performance bonds are required for proposals $150,000 and greater; payment bond only for $35,000 to $150,000.
- Material Quantities: Significant quantities include 106,200 SF of paint, 28,300 SF of LVT, 9,610 SF of Epoxy Resinous Flooring, and 7,000 LF of cove base.
- Product Specifications: Detailed specifications for paint (Benjamin Moore, Sherwin Williams), flooring (Mannington, Johnsonite), and other finishes are provided. Substitutions are generally not permitted due to lead times.
- Environmental Compliance: Contractors must adhere to the "Contractor Environmental Guide" for MCB Camp Lejeune, covering hazardous materials, waste management, and lead-based paint procedures. A hazardous materials plan for lead work is required.
- Personnel: One qualified individual may serve as Superintendent, Quality Control Manager, and Safety & Health Officer.
Submission & Key Dates
- Eligibility: Only T.E. Davis Construction Company, Joyce & Associates Construction, Inc., Olympic Enterprises, Inc., and Quadrant Construction may submit proposals.
- Basis for Award: Lowest Price.
- Proposal Due Date: June 02, 2026, 2:00 PM EST.
- Proposals Email: edward.e.pelser.civ@us.navy.mil and regenia.d.guest.civ@us.navy.mil.
- Requests for Information (RFIs) Cut-off: May 19, 2026, by 3:00 PM EST.
- Site Visit: May 07, 2026, at 1400, meeting at RR139.
- Proposal Acceptance Period: 60 days from receipt of offers.
Important Notes
Offerors are advised that funding may not become available, and no award will be made if funds are not secured. Contractors will not be reimbursed for proposal preparation costs.