Lake Alva Campground Improvements

SOL #: 1240LU26Q0055Combined Synopsis/Solicitation

Overview

Buyer

Agriculture
Forest Service
LOLO NATIONAL FOREST
MISSOULA, MT, 59804, United States

Place of Performance

Seeley Lake, MT

NAICS

All Other Specialty Trade Contractors (238990)

PSC

Repair Or Alteration Of Recreation Facilities (Non Building) (Z2PA)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Apr 29, 2026
2
Last Updated
May 29, 2026
3
Submission Deadline
Jun 8, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The U.S. Department of Agriculture, Forest Service, Lolo National Forest is soliciting proposals for Lake Alva Campground Improvements in Seeley Lake, MT. This Combined Synopsis/Solicitation (RFQ) seeks a contractor to replace the existing water and electrical systems and repave a campground loop. This opportunity is a Total Small Business Set-Aside. Proposals are due June 8, 2026, at 1500 MDT.

Scope of Work

The project involves comprehensive upgrades to the Lake Alva Campground. Key tasks include:

  • Water System Replacement: Replacing all components in the well pumphouse (pressure tanks, flow meter, valves, etc.), installing a new 2" HDPE water main throughout the campground, and abandoning the existing main.
  • Electrical System Upgrades: Demolishing existing equipment, installing new grounding, low-voltage power conductors, cable conduit, box connectors, couplers, new power outlet pedestals, and circuit breakers.
  • Repaving: Repaving sections of the campground asphalt road, patching areas where the new water main intersects the road, and replacing existing wheel stops (Option Item #1). Detailed construction plans (Attachment 4) and technical specifications (Attachment 5) provide specific requirements for site construction, electrical, and water distribution systems.

Contract Details

  • Contract Type: Firm Fixed Price.
  • Magnitude: Between $500,000 and $1,000,000.
  • Period of Performance: July 15, 2027 – December 1, 2028.
  • NAICS Code: 237110 (Water and Sewer Line and Related Structures Construction) with a $45 million size standard.
  • Bonds: A 20% Bid Bond/Offer Guarantee is required with the submission. Performance and Payment Bonds (100% of award price) are required within 10 days after award.

Submission & Evaluation

Quotations are due via email to john.curry@usda.gov by June 8, 2026, at 1500 MDT. Required submission documents include:

  • Price Schedule (Attachment 2)
  • Past Performance/Experience Questionnaire (Attachment 7)
  • Written Technical Approach/Performance Schedule
  • Bid Guarantee Evaluation will be based on a comparative analysis to determine the best value to the Government, considering Relevant Experience, Past Performance, Technical Approach, and Price. Offerors must hold prices firm for 90 calendar days.

Key Clarifications & Site Visit

  • Site Visit: A site visit was scheduled for May 13, 2026, at 10 am at the Seeley Lake Ranger District. Questions can be directed to Brian Story at (406) 529-8534 or brian.story@usda.gov.
  • Campground Closure: Contractors can close camping loops starting August 1st for construction. Notification to the Forest Service is required by March 1st for 2027/2028 closures.
  • Logging Overlap: A logging contract (Richmond Sale) is active until October 2028, with timber operations restricted to September 15th – May 21st, which may impact simultaneous work.
  • Material Handling: Unburnable material must be removed; suitable burnable material can be left on site. Socket fusion is an acceptable pipe joining method. Native soil and salvaged topsoil are acceptable if they meet specifications.

Contact Information

For submission inquiries, contact John Curry at john.curry@usda.gov or 605-673-9216.

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 5Viewing
Combined Synopsis/Solicitation
Posted: May 29, 2026
Version 4
Combined Synopsis/Solicitation
Posted: May 28, 2026
View
Version 3
Combined Synopsis/Solicitation
Posted: May 26, 2026
View
Version 2
Combined Synopsis/Solicitation
Posted: May 26, 2026
View
Version 1
Combined Synopsis/Solicitation
Posted: Apr 29, 2026
View