TINKER AFB MAC BOA WWYK150083 - Repair Transformer Vault 6, B9001
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Air Force is soliciting proposals for Project FA813726R0008, WWYK150083 - Repair Transformer Vault 6, B9001 at Tinker Air Force Base, Oklahoma. This opportunity is exclusively for Tinker AFB MAC BOA holders. The project involves the repair and replacement of critical electrical infrastructure within Building 9001. The estimated magnitude of this construction project is between $1,000,000 and $5,000,000. This is a Total Small Business Set-Aside. Proposals are due by April 10, 2026, at 4:00 PM CST.
Scope of Work
The project requires furnishing all materials, labor, and equipment to repair and replace two gas-filled 2000KVA transformers, associated 480V switch gear (#6C and #6D), all 15KV switches, and the original 3000A tie bus in Transformer Vault 6, Building 9001. Additional work includes repairing interior lighting, adding visual fire alarm notification devices to meet ABA requirements, and repairing the vault's exterior. The Period of Performance is 271 calendar days.
Key Requirements & Clarifications
- Eligibility: This opportunity is restricted to Tinker AFB MAC BOA holders only. Attendance at the initial site visit (held February 5, 2026) was mandatory for eligibility to propose.
- Technical Details: Existing transformers are gas-filled (no PCBs). Busway transition will use custom adapters. Base standard ION8650 meters are expected. Demo work must be phased to minimize production impact, coordinating with the user group. The project follows the 2025 Tinker AFB Electrical Standards. Contractor-installed hoist systems are permitted; the existing hoist beam is damaged. Arc flash mitigation techniques are required, not arc-resistant gear.
- Personnel: Key personnel (Project Manager, Quality Control Manager, Site Safety and Health Officer, Project Superintendent) must meet specific experience requirements.
- Site Access: All personnel require AFMC Form 387 contractor badges and may need escorts for controlled/restricted areas within Bldg. 9001. Entry Access Lists (EAL) and Vehicle Entry Access Lists (VEAL) are required 14 days prior to access.
- Quality Control: The contractor is responsible for a comprehensive inspection system and documentation per specification section 01 45 00.00 10.
- Environmental: No Class 1 Ozone Depleting Substances (ODS) are required. The project considers environmentally preferable purchasing (EPP) and recovered materials.
Contract Details & Timeline
- Contract Type: Solicitation / Request for Proposal (RFP)
- Set-Aside: Total Small Business Set-Aside
- Magnitude: $1,000,000 to $5,000,000
- Performance Period: 271 calendar days
- Liquidated Damages: $277.75 per calendar day for delays.
- Additional RFI Questions Due: March 25, 2026, at 4:00 PM CST.
- Proposal Due Date: April 10, 2026, at 4:00 PM CST.
Submission & Contact
Proposals must be submitted by the deadline. Offerors should refer to Section L (Instructions to Offerors) and Section M (Evaluation Factors for Award) in the full solicitation. Primary Contact: Sara Hinds (sara.hinds.2@us.af.mil). Secondary Contact: Megan Donaghe (megan.donaghe@us.af.mil, 7303205014).