WA FLAP JEFFER 134309(2), Two Trout Creek Culvert Replacement
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Federal Highway Administration (FHWA), Western Federal Lands Division, has issued an Invitation for Bids (IFB) for the Two Trout Creek Culvert Replacement project in Jefferson County, Washington. This Total Small Business Set-Aside opportunity seeks a contractor to replace existing fish barrier culverts with a new fish-passable box culvert, aiming to improve aquatic organism passage and support ecological restoration. The project has an estimated value between $2,000,000 and $5,000,000. Bids are due by April 21, 2026.
Scope of Work
The project, identified as WA FLAP JEFFER 134309(2), involves the comprehensive replacement of two existing culverts on Oil City Road near Milepost 0.5. Key deliverables include:
- Removal of existing culverts and installation of a new precast reinforced concrete box culvert (18-foot span, 12-foot rise).
- Roadway reconstruction, excavation, and stabilization.
- Installation of new guardrails (G4, Type 4, Class B Steel Post).
- Implementation of extensive soil erosion and sediment control measures, adhering to a Stormwater Pollution Prevention Plan (SWPPP) compliant with EPA's Construction General Permit.
- Drainage improvements, including placed riprap, rock weirs, and sediment retention sills.
- Environmental mitigation efforts such as log barriers, root wads, bank stabilization, and planting of various tree and shrub species.
- Temporary traffic control measures.
- The work will utilize U.S. Customary units and adhere to the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-24. The contractor must use the Government's web-based Masterworks system for daily reports.
- The in-water work period has been revised to July 15 to August 31 (inclusive) of any given year, unless approved otherwise by the Contracting Officer (per Amendment A001).
Contract Details
- Contract Type: Firm Fixed-Price
- Set-Aside: Total Small Business Set-Aside (FAR 19.5)
- Estimated Value: $2,000,000 to $5,000,000
- Period of Performance: Work must commence within 10 calendar days after Notice to Proceed, with completion not later than October 2, 2026.
- Place of Performance: Approximately 20 miles south of Forks, Jefferson County, Washington.
Submission & Evaluation
- Bid Due Date: April 21, 2026, 21:00:00Z.
- Submission Method: Electronic bids are NOT accepted. Bidders must submit a printed copy of their bid to the address listed on SF 1442.
- Requirements: A Bid Bond is required (20% of bid price or $3 million, whichever is less). SF 1442 must be fully completed and signed. Representations & Certifications must be submitted online at SAM.gov prior to bid submittal. Offerors must acknowledge receipt of Amendment A001.
- Questions: Technical questions (Plan and Division 100-700 Specification only) must be submitted in writing to wfl.plans-spec@dot.gov five days prior to the due date. General questions can be directed to wfl.contracts@dot.gov or 360-619-7520. Answers will be posted on SAM.gov.
Additional Notes
Prospective bidders are encouraged to review detailed engineering plans, the Stormwater Pollution Prevention Plan (SWPPP), Hydraulic AOP Report, Geotechnical Review Memo, and Survey Control Data available in the attachments. No government personnel will be available for site tours.