BLDG 722 Electrical Installation - April 2026

SOL #: W911RX26QA024Solicitation

Overview

Buyer

DEPT OF DEFENSE
Dept Of The Army
W6QM MICC-FT RILEY
FORT RILEY, KS, 66442-0248, United States

Place of Performance

Fort Riley, KS

NAICS

Electrical Contractors and Other Wiring Installation Contractors (238210)

PSC

Installation Of Equipment: Electrical And Electronic Equipment Components (N059)

Set Aside

Total Small Business Set-Aside (FAR 19.5) (SBA)

Timeline

1
Posted
Mar 24, 2026
2
Last Updated
Mar 30, 2026
3
Submission Deadline
Apr 6, 2026, 9:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of the Army, MICC-FT Riley, is soliciting quotes for electrical upgrades in Building 722 at Fort Riley, Kansas. This Total Small Business Set-Aside opportunity (RFQ under FAR Part 13) requires the installation of a 300 Amp electrical panel, 13 dedicated 20 Amp outlets, and 13 cord reels to support the Synthetic Training Environment-Reconfigurable Virtual Collective Trainer-Air (STE-RVCT-A) suite. Offers are due by April 06, 2026.

Scope of Work

This one-time electrical upgrade involves:

  • Installation of one (1) 300 Amp Electrical Panel, replacing an old amperage panel.
  • Installation of thirteen (13) dedicated 20 Amp electrical outlets with covers, to be installed on pre-existing grid railing at 14 feet high.
  • Provision and installation of thirteen (13) 25-foot cord reels, one for each outlet, suitable for 20 Amps at up to 96% load (SO cord acceptable).
  • Provision and installation of approximately 150 feet of conduit and 150 feet of electrical wiring.
  • All work must comply with NFPA 70E, NEC 70, NEC 70B, and applicable Army Regulations. Power will be supplied from a panel on the North wall, which the contractor is responsible for powering.

Contract Details

  • Contract Type: Request for Quote (RFQ) under FAR Part 13, Firm Fixed Price.
  • Set-Aside: Total Small Business Set-Aside (FAR 19.5).
  • NAICS Code: 238210 (Electrical Contractors and Other Wiring Installation Contractors) with a size standard of $19,800,000.
  • Period of Performance: 7 business days for the one-time upgrade, specifically April 10, 2026, to April 30, 2026.
  • Place of Performance: Building 722, 722 Ray Road, Fort Riley, Kansas 66442.

Submission & Evaluation

  • Offer Due Date: April 06, 2026, at 04:00 PM local time.
  • Required Documents: Offerors must fill out and sign the 'Solicitation - W911RX26QA024' document and the 'Attachment 01 Salient Characteristics Sheet'. Failure to do so will result in non-consideration for award.
  • Submission Method: Email required documents and any other relevant quote documents to the Point of Contact.
  • Evaluation Factors: Minimum Technical Acceptability and Price. Award will be made to the responsible Offeror whose offer is most advantageous.
  • Payment: Via Wide Area WorkFlow (WAWF) system.

Key Dates & Events

  • Site Visit: A non-mandatory site visit is scheduled for March 31, 2026, at 0900 hrs at Bldg. 722, Fort Riley, KS. A maximum of two representatives per Offeror are permitted. No pictures are allowed, and all communication must be in writing.

Additional Notes

  • Contractor personnel require local background checks, AT Level I, iWATCH training, and Information Assurance Technician (IAT) Level I certification. E-Verify must be used for employment eligibility verification.
  • A Quality Control Program (QCP) is required. Insurance (Worker's Comp, General Liability, Automobile Liability) proof is needed within 10 days of award.
  • Refer to 'BLDG 722 Drawings' and 'Elec Install Site Pictures' for visual context and 'Contractor Questions and Answers' for clarifications on technical details like ceiling height (14 ft suspended, 25 ft existing) and power phase (60 hertz single phase).
  • The Wage Determination document (March 24, 2026) outlines minimum wage and fringe benefit rates for Service Contract Act compliance.

People

Points of Contact

Files

Files

Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download
Download

Versions

Version 6Viewing
Solicitation
Posted: Mar 30, 2026
Version 5
Solicitation
Posted: Mar 30, 2026
View
Version 4
Solicitation
Posted: Mar 27, 2026
View
Version 3
Solicitation
Posted: Mar 26, 2026
View
Version 2
Solicitation
Posted: Mar 25, 2026
View
Version 1
Solicitation
Posted: Mar 24, 2026
View
BLDG 722 Electrical Installation - April 2026 | GovScope