DESIGN-BUILD (DB) BARRACKS INITIATIVE (PACKAGE #1), MARINE CORPS AIR STATION (MCAS) CHERRY POINT, NC
Overview
Buyer
Place of Performance
NAICS
PSC
Set Aside
Original Source
Timeline
Qualification Details
Fit reasons
- NAICS alignment with historical contract wins in similar service areas.
- Scope strongly matches core technical capabilities and delivery model.
Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Navy, NAVFACSYSCOM MID-ATLANTIC, is soliciting proposals for a Design-Build (DB) Barracks Initiative (Package #1) at Marine Corps Air Station (MCAS) Cherry Point, NC. This project involves the demolition of five Bachelor Enlisted Quarters (BEQ) buildings and the construction of new facilities to house 1,440 personnel in 720 two-person rooms. This is an Unrestricted, full and open competition. Phase II proposals are due July 07, 2026, at 2:00 PM EDT.
Scope of Work
The project requires Design-Build construction services for the replacement of BEQ 4295 and other facilities. Key deliverables include:
- Demolition of five existing BEQ buildings.
- Construction of new BEQ facilities with 720 two-person rooms to support 1,440 personnel.
- Integration of community and service core areas (laundry, kitchens, administrative offices).
- Provision of a recreation shelter and site amenities.
- Compliance with CMMC Level 1 requirements.
- Specific technical requirements, such as the use of Johnson Controls International (JCI) Metasys for Facility Related Control Systems (FRCS) HVAC.
Contract & Timeline
- Contract Type: Firm-Fixed Price (FFP) Construction Contract.
- Magnitude of Construction: Over $500,000,000.
- Period of Performance: 15 calendar days for commencement, 1461 calendar days for completion.
- NAICS Code: 236220 (Commercial and Institutional Building Construction), Size Standard: $45,000,000.
- Set-Aside: Unrestricted, full and open competition.
- Phase I Proposal Due: April 03, 2026, 02:00 PM local time.
- Phase II Proposal Due: July 07, 2026, 02:00 PM EDT.
- Mandatory Site Visit: June 09, 2026, 11:00 AM local time. Sponsorship requests due by June 05, 2026, 10:00 AM.
- Anticipated Award: September 2026.
Evaluation Factors
This is a two-phase Design-Build procurement.
- Phase I: Evaluated on Technical Approach (Acceptable/Unacceptable), Experience, Safety, and Past Performance. Experience must be within the last 15 years.
- Phase II: Evaluated on Technical Solution, Small Business Utilization and Participation (Factor 6), and Price. Non-price factors (Factors 2-6) combined are significantly more important than price. A minimum of 20% total small business subcontracting is required.
- A compensatory stipend of $200,000 will be provided to unsuccessful Phase II participants.
Key Attachments & Notes
Offerors must submit proposals electronically via PIEE. Required forms include the Small Business Participation Commitment Document (SBPCD), Historical Small Business Utilization, and an Experience Project Data Sheet. A bid bond (SF-24) of 20% of the total bid price or $3M (whichever is less) is required. The Price Proposal Schedule details base bid items and options, including demolition, soil remediation, terrazzo flooring, and an Electronic Security System. All prospective offerors must be registered in SAM.gov.