Risks
- Past performance thresholds may require one additional teaming partner.
- Potential clarification needed on staffing minimums before bid/no-bid.
Next steps
Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.
Quick Summary
The Department of the Interior, Bureau of Reclamation, is soliciting proposals for the N--GC26 SCADA UPS REPLACEMENT project at the Glen Canyon Dam, Page, AZ. This Total Small Business Set-Aside opportunity requires the demolition and removal of the existing SCADA Uninterruptible Power Supply (UPS) system and the installation of a new, brand-name-or-equal UPS system, including all associated electrical work, integration, and testing. Proposals are due by May 26, 2026, at 7:00 a.m. Eastern Time.
Scope of Work
The project involves a comprehensive replacement of the SCADA UPS system. Key tasks include:
- Demolition and removal of the existing SCADA UPS system and associated components, including non-reusable conduit and conductors.
- Provision and installation of a new SCADA UPS system (Schneider Electric 480V UPS with External-Battery, or equal) and all necessary new components, conduit, and conductors.
- Performance of all electrical modifications, terminations, labeling, testing, commissioning, and cutover to minimize downtime.
- Delivery of shop drawings, submittals, factory/start-up support, training for operations staff, acceptance testing, as-built documentation, O&M manuals, and warranty support.
- Compliance with Bureau of Reclamation standards and applicable federal, state, and local codes.
Contract Details
- Contract Type: Stand-alone, Firm-Fixed-Price.
- Period of Performance: 545 days from Notice to Proceed.
- Magnitude of Construction: Between $1,000,000 and $5,000,000.
- Set-Aside: Total Small Business Set-Aside (FAR 19.5). Offerors must be registered in SAM.gov with a valid UEI.
- Bonds: Performance and Payment Bonds (SF25, SF25A) are required. No bid bond is needed.
- Wage Determination: Construction Wage Rate Requirements (Davis-Bacon) apply, specifically AZ20260007 for Coconino County, Arizona (Heavy Construction).
Submission & Evaluation
- Proposal Due Date: May 26, 2026, at 7:00 a.m. Eastern Time.
- Submission Method: Electronically via email to Megan Swift (Megan_Swift@ios.doi.gov). The subject line must be "Bureau of Reclamation Proposal: GCFD POWERPLANT UPS (SCADA EACSS) – 140R4026R0006".
- Evaluation: Award will be made using Best Value-Tradeoff procedures (FAR Part 15). Evaluation factors may include price, technical capability, past performance, and schedule. A Technical Approach (project execution plan, schedule, relevant experience) and Pricing Proposal are required.
- Proposal Acceptance: Proposals must be valid for 60 days.
- Amendments: All amendments, including the latest Q&A and updated drawings, must be acknowledged and submitted with proposals. No additional questions will be accepted.
Additional Notes
A site visit was conducted, and mandatory PPE (safety boots, hard hats, vests) was required for attendees. Detailed Q&A responses and updated drawings have been issued via amendment.