SD FTFW MADI 10(2) & 9000(1) REHAB MADISON WMD HQ ROAD

SOL #: 6982AF26B000008Pre-Solicitation

Overview

Buyer

Transportation
Federal Highway Administration
6982AF CENTRAL FEDERAL LANDS DIVISI
LAKEWOOD, CO, 80228, United States

Place of Performance

SD

NAICS

Highway (237310)

PSC

Construction Of Highways, Roads, Streets, Bridges, And Railways (Y1LB)

Set Aside

No set aside specified

Timeline

1
Posted
Apr 29, 2026
2
Last Updated
Apr 29, 2026
3
Response Deadline
May 14, 2026, 6:00 PM

Qualification Details

Fit reasons
  • NAICS alignment with historical contract wins in similar service areas.
  • Scope strongly matches core technical capabilities and delivery model.
Risks
  • Past performance thresholds may require one additional teaming partner.
  • Potential clarification needed on staffing minimums before bid/no-bid.
Next steps

Validate eligibility requirements, assign capture owner, and schedule partner outreach to confirm teaming strategy before submission planning.

Quick Summary

The Department of Transportation, Federal Highway Administration (FHWA), through its Central Federal Lands Division, has issued a presolicitation for the Rehabilitation of the Madison Wetland Management District (WMD) Headquarters Road in Madison, SD (57042). This project involves pavement reconstruction for the approach road and parking lot of the Madison WMD Headquarters and the United States Fish and Wildlife Service (USFWS) Visitor Center. The estimated cost for this project is between $501,000 and $1,000,000. This is a presolicitation, and plans and specifications are not yet available.

Scope of Work

The project's scope includes:

  • Pavement Reconstruction: Approach road and parking lot, designed with 3.5 inches of asphalt concrete pavement (ACP) over 4 inches of aggregate base material.
  • Safety & Mobility Improvements: Enhanced access and parking for staff and visitors, particularly for the Payne Waterfowl Production Area (WPA).
  • Service Life Extension: Improvements to the access road and parking lot wearing surfaces.
  • Roadway Section: Preservation of the existing two-way, single-lane operation with a consistent 14-foot roadway section, including reconstruction of the approach road apron.
  • Parking Lot Reconstruction: Full reconstruction of the existing parking lot and its asphalt apron, providing eight 10x20 parking stalls (one accessible) on the north side and ten 10x20 stalls on the south side. The parking surface will be regraded to a uniform 1.75% cross slope.

Principal Work Items

Key work items include:

  • Roadway Excavation: 550 CUYD
  • Subexcavation: 200 CUYD
  • Roadway Aggregate, Method 2: 600 TON
  • Asphalt Concrete Pavement: 500 TON

Contract & Timeline

  • Type: Presolicitation (Construction)
  • Estimated Cost Range: $501,000 - $1,000,000
  • Set-Aside: None specified
  • Anticipated Advertisement: May 2026
  • Anticipated Award: July 2026
  • Anticipated Notice to Proceed (NTP): July 2026
  • Anticipated Contract Completion: October 2026
  • Published Date: April 29, 2026

Additional Information

This notice is for informational purposes only and is not an invitation for bid. Plans and specifications are not currently available. Interested parties should monitor SAM.gov for the official solicitation. For inquiries, contact Douglas Whitcomb (cflacquisitions@dot.gov).

People

Points of Contact

Douglas WhitcombPRIMARY
Jorey DemlSECONDARY

Files

Files

No files attached to this opportunity

Versions

Version 2Viewing
Pre-Solicitation
Posted: Apr 29, 2026
Version 1
Pre-Solicitation
Posted: Apr 29, 2026
View
SD FTFW MADI 10(2) & 9000(1) REHAB MADISON WMD HQ ROAD | GovScope